Employee LoginPrimavera
HomeIntroductionProjectsMajor ClientsAbout UsCorporate NewsOrganizationEmployment OpportunitiesPhoto Gallery Contact UsReferencesSite Map  
General Construction HVAC Roofing
Design Build Embassys Worldwide

Renovation Post Theater
Fort Meade, MD






This project was for the addition and renovation to the historic theater originally built in 1927 at Fort Meade. The project included but not limited to the complete interior demolition including asbestos and lead paint abatement, 2,500 sq. ft. addition to the existing theater, built-up roof and shingled roof replacement, mechanical and electrical system rehabilitation, installation of both wet and dry sprinkler systems, installation of public address and sound systems, acoustical wall systems, stage construction, screen and theater lighting systems, storefront and signage.

As prime contractor, Desbuild Incorporated performed all concrete, carpentry, roofing, acoustical wall systems drywall, finishes and the installation of doors and windows. The reference to this project is due to structural roof work. Although this project was not issued as a design/build project, Desbuild was involved in the project from the design phase making all the recommendations. Desbuild helped re-design the complete mechanical system since the original system was not suited for the project. - General Contractor for 7 years



CCSP Pentagon Renovations
Pentagon, VA







Desbuild provided contract management, site management and subcontractor management in addition to self performing over 20% of the work with its staff. Several task orders were completed in occupied spaces and the work schedule involved both normal working hours and off hours. Desbuild worked closely with both the client and occupant to avoid any stoppage of normal work. In addition, Desbuild performed several projects during weekend hours.


Task 1 $100,000.00 CCSP Trailer Installation
Task 2 $22,600.00 Repair Steam Vent/Roof
Task 3 $2,750,000.00 J2T NIMA Swing Space Renovations, Wedge 3
Task 4 $859,306.00 Renovations to PFPA-OCC
Task 5 $120,000.00 Waterproofing Corridor #2 Bridge
Task 6 $62,000.00 Tiger Team Double Wide Site Work
Task 7 $198,000.00 Repair MOC Roof


Biological Safety Lab, Building 54
Walter Reed Army Medical Center, MD







The highlights of this project involved construction of a new 3,000 square feet biological safety lab at Walter Reed Medical Hospital, 5th Floor, Washington, DC.

The work included concrete, interior finishes, resinous flooring, VAC, plumbing, electrical systems, piping, chiller installation, laboratory furnishings including centrifuges, bio cabinets, incubators etc. The project required extensive project management, supervision and subcontractor coordination due to the schedule and working in an occupied space.



Renovate Lobby and Mezzanine,
Lafayette Building
Washington, D.C.






This project involved providing the labor, material, equipment and supervision to renovate lobby and mezzanine at the Lafayette Building, 811 Vermont Avenue, NW, Washington, DC.

Work included but not limited to: Refinish wood veneer in elevator cabs, refinish metal bronze surfaces inside the elevator cab, cut excess black iron existing inside the cove at he main lobby, allowing installation of new cove lights, change drinking fountain's finish from specified stainless steel finish to bronze finish, refinish four sets of existing front entrance door, refinish existing four sets of double doors in satin finish in lieu of mirror finish.



Renovate Park Police Headquarters
Mclean, VA








This project was for the addition and renovation of the Park Police Headquarters at Turkey Run Station, McLean, VA.

The project included a new addition of 8,000 square feet of office space. Sever features included: security control room, high-density material that can absorb bullets from gun fire, bullet proof storefronts and pass through window, cooper roof, new security system, mechanical system, new emergency generator and fire alarm system. There is a state-of-the-art Siemen's security system. This system works close circuit television, controlled electric locks and a card reading system. With this security system, Siemen's supplied the fire alarm system. The National Park Police will be networked from the Anacostia station when it is completed. The holding cells have installed glazed CMU with stainless steel plumbing fixtures that are operational from outside the cell. Also, installed special holding cell doors and frames.



Construct Emergency Operations Center,
HH Building
Washington, D.C.








The project involved the construction of a new command operations center for the Dept. of Health & Human Services. The project was Fast Tracked (45 days) in an occupied building and included: demolition, gyp board work, mechanical, electrical, acoustic wall, acoustic ceiling, mill work, access flooring, painting, carpet and flooring, doors and hardware, sprinkler, and wood panel. The project required extensive project management, supervision and subcontractor cooperation due to the accelerated schedule.



Renovation of East West Wing Roof, the White House
Washington, D.C.

The project involves the renovation of the West Terrace, Upper West Terrace, West Wing Balcony Roof, West Wing Office Roof, West Wing Canopy Roof, East Terrace, East Wing Office Roof, and the East Wing Canopy Roof of The White House in Washington, DC.

Additional work includes the renovation of permanent stairs on the East and West Wing, and replacement of temporary stairs on the West Wing Roof. The Mansard roofs on the West Wing and East Wing will be retained.



EPA Emergency Command Center, Design/Build
Washington, D.C.






This project involved the design and construction of a new emergence operations center for the Environmental Protection Agency at the Ariel Rios Building in Washington, DC.

Phase I involved the necessary planning, scheduling, procurement and renovations of existing basement areas to meet all requirements for enhancement and upgrade of the present emergency operations center and new designs involving architectural, structural, mechanical, plumbing, and electrical work.

Phase II involved the construction of the new center and included: demolition, gyp board work, mechanical, electrical, acoustic wall, acoustic ceiling, mill work, access flooring, painting, carpet and flooring, doors and hardware, sprinkler, and wood panel. The project was Fast Tracked for seventy-five (45) days. The project required extensive project management, supervision and subcontractor coordination due to the accelerated schedule.



Checkpoint Building, Social Security Complex
Woodlawn, MD




Desbuild Incorporated was the prime contractor for this project. The project was for the construction of a glass panel/aluminum panel building, which acted as a checkpoint building for the National Computer Center.

The project included a 6,000 square foot, state-of-the-art visitor control center and new vehicle turn around and checking lanes. The building included automatic turnstile systems; complicated security system with retina scanners; mechanical systems tied to the base ATC system; and a fire alarm and Trane tracer system.

As prime contractor, Desbuild self performed drywall, painting, carpentry, EPDM Roofing and metal wall panels with 58% subcontracted including but not limited by design, electrical, mechanical, HVAC, specialty trades, etc. Desbuild performed all contract management, safety, and quality control management for the project.



Military Police Station, Design/Build
Fort Belvoir, VA






This project included the complete design and construction of 10,000 sq. ft. of office space; construction of new gabled roof, brick masonry walls, installation of doors and windows, installation of new mechanical and electrical systems, plumbing and underground utilities. The reference to the proposed project is: building construction, site work, mechanical/electrical and roof system.

As prime contractor, Desbuild self-performed carpentry, installation of roof trusses, standing seam metal roof, EPDM roof, and standing seam, drywall, finishes and the installation of doors and windows. Desbuild subcontracted 55% including but not limited to mechanical, electrical, masonry and structural steel.



Child Development Center, Design/Build
Suitland, MD








This project included design and construction of 7,800 square foot Child Development Center. The building shell was constructed using a pre-engineered building.

The Scope of work included: grading, site preparation, storm water management system, 2,400 linear feet of sewer lines, 1,200 linear feet of electrical duct-banks; water line,; masonry, site and building concrete, asphalt paving, landscaping, structural steel work, doors, windows, storefront, interior partitions and painting, carpet, vinyl and ceramic flooring, cabinets and case work, sprinklers, firm alarm system, HVAC, plumbing, exterior and interior electrical work, installation of new transformer.



U.S. Embassy, Design/Build
Manama, Bahrain



Desbuild Incorporated recently completed Interior Renovations for the U.S. Department of State Office of Overseas Building Operations (OBO) at the U.S. Embassy in Manama, Bahrain.

This Design/Build project was awarded under a multiple-year IDIQ contract.

The project consisted of interior renovations on the first, second and third floor of the Embassy, including all associated architectural and MEP work.

Renovations on the first floor included modifying existing space to accommodate new office areas, as well as addition of a custom-fabricated FE/BR entry to match the original construction of existing adjacent doors.

Renovations on the second and third floor were in secure CAA areas, requiring secured shipment of materials and the use of cleared U.S. personnel.

The project required close coordination with both OBO and the Post due to the sensitivity of the work areas and changing conditions of the contract during the duration of the work. During construction, changing security requirements and revisions to areas of operation necessitated a re-sequencing and phasing of the project. This was accomplished "on the fly" through close coordination with both OBO and Post, resulting in minimal impact on day-to-day operations of the Post.



U.S. Embassy, Design/Build
Buenos Aires, Argentina




Desbuild Incorporated is the Design/Build Contractor for the Security Upgrades project at the US Embassy, Buenos Aires, Argentina. Desbuild was responsible for full design from bridging documents and construction under a lump sum contract.

Key elements of this 16-month project include:
  • Design and Construction of a new anti-ram/anti-climb wall along the entire length of the back of the compound. The work had to be carefully designed to not interfere with existing Post underground utilities and an existing neighboring wall that had been deemed an historic landmark.
  • Replacement of approximately 140 existing windows with new FEBR windows while space is fully occupied.
  • Construction of a new PAC area within the busy Consular area, requiring minimum interference and shut-down
  • Physical security upgrades at generator room and along other high-risk perimeter areas.
  • Relocation of existing and installation of new underground utilities

This project is being constructed without the benefit of on-site OBO personnel, requiring close coordination and communication directly with the Post. All work has performed with no adverse shut-downs or interruption to daily ongoing activities.

Local professionals were engaged to facilitate construction activities along the historic structure and work with local agencies. Desbuild Incorporated also managed to sequence the project in such a way that an initial OBO planned movement of personnel to swing space would not be required, considerably easing logistic issues for the Post.



U.S. Embassy, Existing Office Building
Chennai, India






Desbuild - L&T ECCG Joint Venture was the prime contractor for this project at the Consulate in Chennai, India.

The Consulate is 7,063 square meters and consists of three stories, plus a basement. The entire structure was to be renovated. Each floor, including the basement, required new ceilings, new lights, and power distribution, telephone, fire alarm, and data lines furnished and installed. The existing interior partition walls on the first and second floors were demolished and new layouts constructed. The basement and third floors had minor interior partition wall demolition and new construction. All bathrooms were renovated. A new chilled water fan coil unit air-conditioning system was installed and the existing chillers remained.

Two new compound access control structures, totaling more than 260 square meters were constructed; in addition, a new entrance to the Consulate was constructed. Also, a new parking lot with twenty-five parking spaces was constructed.



U.S. Embassy
Mumbai, India






Desbuild Incorporated was the prime contractor for this project at the USIS Building in Mumbai, India. The USIS building is situated 500m from the busy Church gate Railway Station of Mumbai and all material, machinery and manpower had to be scheduled and coordinated with the post security while keeping in mind the local traffic regulations.

The work performed at the project site was subjected to security requirements and restrictions in accordance to new State Department regulations. Mobilization and preliminary work, including demolition, cleaning, grading and similar work for temporary facility and initial construction were performed without penetrating secure areas and with low level security restrictions. The General construction work not involving installation of classified materials and services but including construction to integrate new work with the existing facility required, when necessary, cleared US citizens to complete the scope-of-work. Desbuild provided its employees and subcontractors who held the required security clearance levels.

Special recognition was given to Desbuild Inc. for execution without disrupting the normal working of the building that houses the local offices of the US Public Affairs Office, American Information Resource Library, and US Educational Foundation in India, US Foreign Agricultural Office, and the US Commercial Service. None of the utilities to the building including Electricity, Water, Sewer and air conditioning was put out of service for a single day. The AIRC Library has about 500 visitors a day apart from the staff of about 75. Work was executed without causing any disturbance to the tenants, visitors and neighbors. This included nighttime and weekend working.



U.S. Embassy
New Delhi, India






Desbuild Incorporated, acting as a General Contractor, recently completed the Compound Access Control (CAC) Facility Project for the U.S. Department of State Office of Overseas Building Operations (OBO) at the U.S. Embassy in New Delhi, India.

This 12-month multi-million dollar project, part of the DOS worldwide security upgrade program, consisted of installation of various force protection measures and construction of new CAC facilities at ten key entry and exit points to both the Residential and Chancery Compounds, including the Ambassador's residence.

In its role as General Contractor, Desbuild Incorporated's full time on-site management staff was responsible for proper coordination, scheduling and execution of all construction activities of all its subcontractors, who span all 16 Construction Divisions. Due to the nature of the work and its obvious impact on Compound Security, it was essential that Desbuild maintain close contact and coordination with various Compound agencies through OBO.

One of the more challenging aspects of the project was the proper phasing and sequencing of the work at each gate. The project was broken down into multiple phases and sub-phases, requiring careful planning and extensive cooperation and coordination with the Post. Throughout the project, Desbuild worked closely with OBO and the Post to minimize or eliminate any interruption to ongoing activities, while maintaining key necessary security requirements.



U.S. Embassy
Katmandu, Nepal







Desbuild Incorporated is currently engaged as the prime contractor for Physical Security Upgrades at the US Embassy Compound, Katmandu, Nepal.

This 18-month multi-million dollar project, part of the DOS worldwide security upgrade program, consists of: installation of various force protection measures, vehicular and pedestrian construction of new CAC facilities at key entry and exit points construction of a new warehouse facility construction of new and enhancement of existing anti-ram walls installation of a new underground fuel storage and distribution system upgrade of security at various existing structures underground utilities

The project covers 2 compounds and requires work across all trades. Multiple phases and sub-phases are being employed to ensure productivity and minimal impact to ongoing Post activities.

One of the many challenges of this project is the supply of materials due to its remote location, complicated by ongoing political strife. This has made both the importation of US procured materials as well as locally supplied materials particularly challenging and has required creativity on the part of the on-site team to re-sequence from time to time to maintain flow of activity.

Desbuild has continued to work closely with both the Post and OBO, as it has uncovered existing found conditions requiring re-design. Desbuild, working with its subcontractors' engineers has brought multiple solutions to the table with each encounter. This has shortened the decision-making time for OBO/Post considerably and has allowed the work to continue on schedule, despite the interruptions.